OLVIA Signs Phase 2 Expansion Design Contract
June 2026
OLVIA S.R.L. is pleased to announce the signing of a design contract for Phase 2 of our Galați Free Zone refinery expansion.
Design work will be carried out by Thesikkoffice SRL — our general design partner responsible for the Phase 1 facility currently under construction.
Phase 2 Additions
- +200 TPD additional refining capacity
- +200 TPD additional bottling capacity
- +5,000 t bulk storage (oil tanks)
- Several thousand m² of additional warehousing and bottled goods storage
Combined Facility Upon Phase 2 Completion
| Phase 1 (launching Q4 2026) | Phase 2 (design in progress) | |
|---|---|---|
| Refining capacity | 200 TPD | 400 TPD |
| Bottling capacity | 100 TPD | 300 TPD |
| Bulk storage | 3,500 t | 8,500 t |
Timeline
Design work commences immediately. Construction will follow upon design completion and approval.
Phase 1 commercial production remains on schedule for Q4 2026 / Q1 2027.